Vacant land – conditions on development [GN19]

PDF 500KB

Last update: 1 July 2016

Foreign persons are generally required to notify and receive a no objection notification before acquiring an interest in vacant commercial or vacant residential land in Australia, regardless of the value of the proposed acquisitions ($0 threshold). Such proposals are normally approved subject to development conditions.

Land is vacant if there is no substantive permanent building on the land that can be lawfully occupied by persons, goods or livestock.

This Guidance Note outlines the conditions that will normally apply to a no objection notification for foreign investment in vacant land.

Vacant commercial land

Vacant land would be considered to be commercial land if it is land in Australia or the seabed of the offshore area, other than land:

  • used wholly and exclusively for a primary production business; or
  • on which the number of dwellings that could reasonably be built is less than 10.

No objection notifications to acquire vacant commercial land will normally be subject to conditions that the foreign person:

  • commences continuous construction of the proposed development on the land within five years of the date of approval; and
  • does not sell the land until construction is complete.

Example 1

A property developer is seeking to purchase vacant land to develop into an apartment complex. The developer wishes to sell the apartments off the plan. The approval to purchase the land would normally be subject to a condition that the land not be sold until construction is complete. The developer would not breach this condition by selling the apartments off the plan as apartments sold off the plan are not considered sold until the development is complete and settlement takes place.

In exceptional circumstances where conditions cannot be met, foreign persons may apply for a variation to the conditions of the no objection notification. A fee will apply for this. Applications for variations will be considered on a case-by-case basis with regard to:

  • why construction of the development was unable to commence within the time stated in the approval. Significant and unexpected delays to processes by relevant local government authorities, failure of key businesses involved in the supply of trade services, and unexpected and extensive delays in sourcing core materials would normally be considered genuine reasons for delay;
  • the length of time expected to be required to commence construction of the development;
  • whether variations extending the time period for commencing construction had previously been granted for the specified development; and
  • the compliance history of the applicant, and any related persons or entities.

Foreign persons would normally need to demonstrate extenuating circumstances to change the condition to allow them to sell land prior to finalising construction, as actions involving land banking are inconsistent with the national interest and Australia’s foreign investment framework.

For more information on variations, see Guidance Note 40.

Vacant residential land

Proposals to acquire vacant residential land for dwelling development will normally receive no objection notification subject to conditions that:

  • the development is completed within four years from the date of approval; and
  • evidence of completion of the dwellings is submitted within 30 days of being received. This could include a final occupancy or builder’s completion certificate.

In exceptional circumstances where the development cannot be completed within the specified four year condition, foreign persons may apply for a variation to the conditions of the no objection notification. A fee will apply for this. Applications for variations will be considered on a case-by-case basis with regard to:

  • why the development was unable to be completed within the four year time frame. Significant and unexpected delays to processes by relevant local government authorities, failure of businesses involved in the supply of trade services, and unexpected and extensive delays in sourcing core materials would normally be considered genuine reasons for delay;
  • the length of time expected to be required to complete construction of the dwelling;
  • whether variations extending the time period for completion had previously been granted for the specified dwelling; and
  • the compliance history of the applicant, and any related persons or entities.

For more information, see Guidance Note 10.

Penalties

Persons who fail to comply with conditions of a no objection notification may be subject to strict penalties (including civil and criminal penalties).

Further information

Vacant commercial land

Further information is available on the FIRB website or by contacting +61 2 6263 3795.

Vacant residential land

Further information is available on the FIRB website or by contacting 1800 050 377 from Australia or +61 2 6216 1111 from overseas.


Important notice: This Guidance Note provides a summary of the relevant law. As this Note tries to avoid legal language wherever possible it may include some generalisations about the law. Some provisions of the law referred to have exceptions or important qualifications, not all of which may be described here. The Commonwealth does not guarantee the accuracy, currency or completeness of any information contained in this document and will not accept responsibility for any loss caused by reliance on it. Your particular circumstances must be taken into account when determining how the law applies to you. This Guidance Note is therefore not a substitute for obtaining your own legal advice.